Development Project Timeline 2004
| Saturday, June 12th |
Convert Bio data, but continue refresh
|
| Friday, June 25th |
Go-live with Gift (systems will be taken down for
a day)
Refreshes for gift and bio hault |
| Saturday, June 26th |
Test and Trouble shoot Gift conversion |
| Sunday, June 27th |
Test and Trouble shoot Gift conversion |
| Monday, June 28th |
Double entry gifts and bio data in both Advance
and HP;
Start using new acknowledgment system for gifts |
| Tuesday, June 29th |
Double entry of gifts and bio data in both Advance
and HP |
| Wednesday, June 30th |
Double entry of gifts and bio data in both Advance
and HP |
| Thursday, July 1st |
Official, public Go-live! Only enter gifts and
bio data in Advance! |
|
|
|