University of Notre Dame Mark renovare logo

 

 


 

 

Team Reports - September 2003 Renovare Huddle

October 30, 2003

Finance

Vic DeCola and Mike Geglio, the leads of the Renovare Finance team reported that the first draft of the chart of financial accounts had been loaded into Banner. They said work was progressing on Endowment financials and that baseline Banner meets at least 80% of our endowment business process.

One of the biggest challenges, according to DeCola and Geglio, is dealing with simultaneous critical paths. Also, there are some deliverables that still lack definition of standards and scope, and too often, critical training schedules leave little time for working on the deliverables.

Increasingly, communications will become a critical success factor according to the Finance Team leads. Both inter-project and external cross-campus communications are in direct proportion to the scope of the project, they said.

-----------------------------------

Development Team

Team leads Katherine Rosswurm and Donna Adams reported that all of the ACT demographic and biographic data has been converted, and now is available through the Advance Oracle application and is refreshed nightly. In addition, eight of the 13 ACT databases used by regional development directors have been converted to Advance as of September 25, 2003. Advance is a user interface from Sungard BSR Inc. used to manage and access data stored in Oracle databases.

Adams and Rosswurm noted all 13 of the ACT databases were a little different, which meant that each conversion had its on challenge.

The team leads said there had been strong support from Notre Dame database personnel that the Development Team had benefited from a knowledgeable Sungard BSR consultant, although earlier on, there had been excessive turnover among of the vendor-assigned consultants.

Lessons learned, according to Adams and Rosswurm, including the need for ongoing communications among constituents in the Development Department and the importance of going through all of the steps specified in the planning process.

Sponsorship, too, is critical to the success of the Development Team’s effort. Toward that end, Rosswurm announced that David Morrissey, senior director of University Relations had assumed the role of Development sponsor.

-----------------------------------

Ancillary Team

The Health Services implementation went live on May 24, 2003 said John Kelly, the technical lead for the Ancillary Team.

The new Health Services systems shows on screen who is scheduled to come in for appointments, and enables ND healthcare personnel to enter a diagnosis code(s) for services and automatically post charges to the appropriate student account.

Kelly said the Security Dispatch system, which went live on August 4, 2003, enables dispatch personnel to log minor events, such as building checks and also maintain records on more serious offenses that are considered an actual crime. Dispatchers also can see in real time the location of campus security officers, and thereby, dispatch the officer that’s closest to a logged event. >>more

 

(Ancillary Team continued) Some of the more positive elements of developing and implementing the Health Services and Security Dispatch systems included weekly technical team meetings with OIT database personnel and representatives from OIT Operations and Engineering, Information Security and Network Engineering. Another plus was the development of training scripts for system training, according to Kelly.

Still, there were some things that could have gone more smoothly, Kelly said. Approaching training of end user personnel on a need-to-know basis instead of immersing users in every aspect of the system, for example, would have saved time and provided a better experience for users, Kelly explained. Also, Kelly said, the team learned through experience to set expectations for time available among functional personnel.

-----------------------------------

Information Delivery Team

Technical lead Dale Carter said the catalog of finance core operational reports was complete.

Carter added that her team had been successful in hiring and team building. Of particular value, according to Carter, were the site visits her team made at the University of Illinois and Wayne State University.

-----------------------------------

Infrastructure Team

“The more we looked at Banner, the more it looked like a database application, said Steve Tapp, technical lead for the team. Because of that, Bruno Zovich will now serve share technical lead duties with Tapp.

The Infrastructure Team was the first team out of the gate, according to Tapp. “We were running around doing Banner installation work the week of June 2 during the Renovare kickoff.

There now is a virtual private network (VPN) set up to provide secure access to Banner development server, Tapp noted. Also, the consulting firm Collegis is now on site to help with help with infrastructure development.

Although Banner training is now well under way, Tapp said decisions on the production platform caused some delays in training. There also are some personnel backfill challenges going forward as more of OIT’s operations and engineering people are transferred to the Renovare project, Tapp added.

Related Stories:
>>Renovare Teams Review Progress at Quarterly Huddle
>> Keep the Vision (presentation by Chuck Lennon)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Notre Dame Home
University of Notre Dame
Notre Dame, Indiana 46556
Phone: 574-631-5000
Copyright ©2002 University of Notre Dame
Last modified: Thursday, November 13, 2003