| Status Date: |
5/23/2001 |
Current Phase: |
Concept |
Project Name: Institutional File Space
Project Purpose & Benefits:
* this should be bullet point executive level descriptions limited
to the key items.
- complete solution for the implementation of an Institutional
File Space, and associated administrative policies and procedures
- where possible, provide a closer match between client systems
and the network storage that services them
|
Project Status
| |
Schedule:
|
Project Milestones
|
Tollgate Delivery
|
Forecast Date
|
| *milestones for next phase |
|
|
| |
|
|
| *Future tollgates |
|
|
| Technical Solution delivery |
|
|
| Project closure |
|
|
Budget:
| Tollgate approved dollars |
$0,000
|
| Forecast dollars |
$0,000
|
|
Key Accomplishments:
* this should be bullet point items that are key to understanding
the progress
- Second stakeholders meeting held and minutes posted (5/3/2001)
|
Issues:
* this should only be those issues that you need additional assistance
with
- Need to re-evaluate the project direction (due to feedback from
stakeholders)
|
Next Steps:
* this should be bullet point items that are key to understanding
the milestones to the next phase
- Schedule meeting to discuss project direction
- Validation of project assumptions made in the charter
- Need to redefine (with Stakeholders) and document, specifically,
the critical requirements of the project
|
|