Skyway Bridge Briefing



Major work underway at time of visit was concerned with foundations:

1. Coffer cells are used to permit excavation.
2. Prefabricated footing boxes (800 tons) serve as a template through which large piles are driven.
3. A template frame is constructed supported on smaller pilings while actual main piies are driven.
4. Each pile is then welded to the footing box.
5. Piles are excavated, rebar cages are slid in and filled with concrete.

Bridge piers are then cast in place and topped by deck segments cast at an offsite yard and brought in by barge.